Peninsula Boardwalk Emergency Repairs

To view a larger image, right-click the image and select "open image in new tab".

Background

Constructed in the 1920s, the Peninsula boardwalk spans approximately 3,600 feet, running along the oceanfront between 55th and 69th Place.

In early September 2026, Hurricane Marie brought an unusually large, long-period southerly swell and elevated tides to the Peninsula, resulting in substantial beach erosion that exposed portions of the normally buried bulkhead. Waves of 8 to 10 feet overtopped and eroded the sand berm between 63rd Place and 68th Place and damaged portions of the wooden boardwalk. City staff  implemented emergency stabilization measures, and the boardwalk remains closed for further assessments.

The Department of Public Works is working with on-call contractor Bitech Construction to complete the necessary repairs. These repairs are intended to restore safe and equitable access to the beach, waterfront and residences in the area while the City continues to evaluate ongoing shoreline erosion and stabilization measures. Given the boardwalk’s age and deteriorated condition, improving its resilience to future storm events is crucial to limiting further damage. These are emergency repairs to address storm damage sustained from Hurricane Marie and from other weather extremes caused by the super-strength El Niño event and are separate from any long-term replacement projects for the boardwalk.

Repair work began October 16, 2026, with activities proceeding as tidal and site safety conditions allow. If necessary, work may be temporarily halted until additional sand from the Alamitos Bay Entrance Channel Dredge project is placed to protect both the crews and the construction in progress.

The City will continue to monitor storm conditions throughout the 2026-2027 El Niño season, and updates will be posted on this page as work progresses.

Timeline

Construction Start October 2026
Construction End TBD

Project timeline is set barring weather delays and other unforeseen circumstances. 

Objectives

  • Provide safe passage along the beachfront for residents and visitors, including people using mobility devices, strollers and wagons
  • Repair storm damage to the boardwalk and bulkhead
  • Stabilize the boardwalk and bulkhead throughout the storm season

Project Features

  • Boardwalk Deck: Replacement of damaged boardwalk decking and supporting stringers, with full-width boardwalk replacement assumed for the identified lengths.
  • Bulkhead: Replacement of deteriorated cap side plates (waterside and landside) and cap top plate as well as the replacement of missing/damaged vertical bulkhead planks, plus new bulkhead sandwich reinforcement planking at select locations.
  • Bulkhead Wall Sections: At two locations with a complete missing section of bulkhead wall, full-height reconstruction of the wall section, including new vertical planking, blocking, and whale beam, tying into competent existing bulkhead on each side.

FAQ

Project Funding

This project is funded by the Tidelands Emergency Reserves.