Peninsula Boardwalk Emergency Repairs
To view a larger image, right-click the image and select "open image in new tab".
Background
Constructed in the 1920s, the Peninsula boardwalk spans approximately 3,600 feet, running along the oceanfront between 55th and 69th Place.
In early September 2026, Hurricane Marie brought an unusually large, long-period southerly swell and elevated tides to the Peninsula, resulting in substantial beach erosion that exposed portions of the normally buried bulkhead. Waves of 8 to 10 feet overtopped and eroded the sand berm between 63rd Place and 68th Place and damaged portions of the wooden boardwalk. City staff implemented emergency stabilization measures, and the boardwalk remains closed for further assessments.
The Department of Public Works is working with on-call contractor Bitech Construction to complete the necessary repairs. These repairs are intended to restore safe and equitable access to the beach, waterfront and residences in the area while the City continues to evaluate ongoing shoreline erosion and stabilization measures. Given the boardwalk’s age and deteriorated condition, improving its resilience to future storm events is crucial to limiting further damage. These are emergency repairs to address storm damage sustained from Hurricane Marie and from other weather extremes caused by the super-strength El Niño event and are separate from any long-term replacement projects for the boardwalk.
Repair work began October 16, 2026, with activities proceeding as tidal and site safety conditions allow. If necessary, work may be temporarily halted until additional sand from the Alamitos Bay Entrance Channel Dredge project is placed to protect both the crews and the construction in progress.
The City will continue to monitor storm conditions throughout the 2026-2027 El Niño season, and updates will be posted on this page as work progresses.
Timeline
| Construction Start | October 2026 |
| Construction End | TBD |
Project timeline is set barring weather delays and other unforeseen circumstances.
Objectives
- Provide safe passage along the beachfront for residents and visitors, including people using mobility devices, strollers and wagons
- Repair storm damage to the boardwalk and bulkhead
- Stabilize the boardwalk and bulkhead throughout the storm season
Project Features
- Boardwalk Deck: Replacement of damaged boardwalk decking and supporting stringers, with full-width boardwalk replacement assumed for the identified lengths.
- Bulkhead: Replacement of deteriorated cap side plates (waterside and landside) and cap top plate as well as the replacement of missing/damaged vertical bulkhead planks, plus new bulkhead sandwich reinforcement planking at select locations.
- Bulkhead Wall Sections: At two locations with a complete missing section of bulkhead wall, full-height reconstruction of the wall section, including new vertical planking, blocking, and whale beam, tying into competent existing bulkhead on each side.
FAQ
The City is pursuing a seven-point plan that combines immediate bulkhead repairs, beach nourishment, interim protective measures, and long-term adaptation planning along with necessary funding strategies. The first point of this plan is repairing and rehabilitating the bulkhead and boardwalk system along the Peninsula, from 62nd Place to 68th Place.
The plan is under active review while the City assesses the full extent of additional damage from ongoing weather events most recently due to Tropical Storm Rachel. Work will begin with a monitored start to confirm conditions are suitable for a safe and efficient work environment. If necessary, work may be re-sequenced or temporarily halted to enable work in a dynamic tidal environment
The Long Beach Department of Public Works is overseeing various efforts and projects in preparation for and response to weather events. Bitech Construction and subcontractor, Power Engineering Construction are supporting the bulkhead repair work.
Bitech Construction andsubcontractor Power Engineering Construction have mobilized and begun preparing materials for construction as of October 16. Completion is anticipated by the end of the year. The date will be confirmed once the team has assessed the damage caused by ongoing weather events following Hurricane Marie. Based on observed damage during Tropical Storm Rachel, additional assessments by Building & Safety in the Community Development Department may need to inform where repairs can be safely performed. While it is Public Works’ intent to rebuild and rehabilitate all damaged portions of the bulkhead/boardwalk prior to the end of the year, sequencing may be dependent on access and addressing conditions on adjacent private parcels.
The current estimated cost is approximately $3.6 million. This amount is subject to change and dependent on assessment of the full extent of current and potential future damage caused by weather events.
This is to be funded from the Tidelands Emergency Reserves. City of Long Beach General Fund and City emergency reserves will not be used.
The work may include:
- Repairs to the bulkhead cap, vertical planking and whale beams
- Replacement of damaged decking and stringers
- Replacement of deteriorated or missing pile caps and hardware
- New toe kicks where they are currently missing
- Full-height bulkhead reconstruction at two locations with missing sections of bulkhead (near 64th Place and near 67th-68th Place)
- Repair of a previously damaged bulkhead at 62nd Place
The heaviest work is expected to take place between 64th and 68th Place, where full-section deck, stringer and pile cap beam replacement is needed. Lighter, targeted repairs are needed west of 63rd Place and east of 68th Place. The scope of work may be revised after a full assessment of the damage from Tropical Storm Rachel.
New lumber will be pressure-treated Douglas Fir Larch with hot-dip galvanized fasteners and hardware, consistent with the existing construction. Removed lumber that is still structurally sound may be inspected and reused in place.
Additionally, as described in the City’s memorandum on the Peninsula, many of the embedded piles that support the pile caps, stringer and boardwalk deck were determined to be reusable. After Tropical Storm Rachel, the conditions of the piles will need to be evaluated given the sustained impacts from swells and possible movement of adjacent foundations.
The work is highly tide-dependent, and bulkhead repairs must occur during low tides, so work outside standard hours may occur to expedite progress. Other work that may occur during high tide including demolition and removal of damaged members.
They are separate projects and were necessitated from different circumstances. The maintenance dredging project was initiated in 2023 to restore navigable dredge depths within the Alamitos Bay entrance channel and is expected to utilize dredge spoils as beach nourishment material along the Peninsula.
The bulkhead/boardwalk repairs are emergency repairs, which were initiated after Hurricane Marie, and the scope is expected to expand to address damage encountered after Tropical Storm Rachel. The nourishment project may support conditions to better facilitate bulkhead repair construction.
The City, working with coastal engineering firm Moffatt & Nichol, is designing a low-profile rock revetment to be placed along the most vulnerable areas of the Peninsula. The rock revetment is expected to dissipate wave energy and reduce direct impacts to the bulkhead in the face of future storms, southerly swells, and in a scenario of rapid coastal erosion. This is the fourth point of the City’s seven-point plan responding to Hurricane Marie and subsequent weather events.
Project Funding
This project is funded by the Tidelands Emergency Reserves.
More Information
- 09-25-2026 Memorandum: Peninsula Update – Hurricane Marie Response
- Construction Notice - Peninsula Boardwalk Emergency Repairs
- 09-22-2026 City Council Special Meeting - Staff Report
- 09-22-2026 City Council Special Meeting - Proclamation of Local Emergency
- 09-22-2026 City Council Special Meeting - Resolution 26-0139
Contact
For project inquiries, please contact TidelandsCIP@longbeach.gov.
For media inquiries, please contact lbpwmedia@longbeach.gov.
Project Updates
Week of 11/9/26
Emergency boardwalk repairs continue in the 66th Place block this week. Crews will be working daily from 6:30 a.m. to 3 p.m. as improvements progress.
Week of 11/2/26
Emergency repairs to the Peninsula Boardwalk continue between 66th and 67th Place. Crews are installing vertical bulkhead boards and whale beams, repairing the cap, and installing sandwich plates to reinforce the boardwalk structure and support its long-term stability. Daytime working hours are expected for the duration of the boardwalk and bulkhead repairs.
Week of 10/26/26
The Peninsula Boardwalk Emergency Repairs project continues during low tide and will continue until repairs are complete and depending on safety conditions in the work zone.
Current schedule (subject to change):
Work is scheduled from 2 p.m. to 10:30 p.m. Crews are conducting cap repair, excavation and installation of vertical bulkhead boards, cap plates and additional sandwich boards between 66th and 67th Place. Over 40,000 linear feet of lumber has been ordered for repairs thus far.
Week of 10/19/26
The repair project began on October 16, with work scheduled to continue during morning and evening low tides. Contractors’ work hours will vary week to week to optimize the low tide working windows.
Current schedule (subject to change):
Work scheduled from 8 p.m. to 4:30 a.m. Crews are currently working between 67th Place and 68th Place.
Work activities:
- 6735 E. Seaside Walk: Cap repair and excavation moving west
- 6717 E. Seaside Walk: Vertical bulkhead boards, cap plates and additional sandwich boards installed
- 6701 E. Seaside Walk: Cap plate installation beginning
Due to safety concerns associated with red-tagged buildings, no work is permitted between 64th Place and 66th Place at this time. This area is to remain restricted for a minimum of two weeks, pending clearance from the City’s Community Development Department.
Work areas and schedules are subject to change as conditions are assessed and repairs progress.
For additional information about the project, timeline, cost and other frequently asked questions, please refer to the FAQ above.
Public Works has performed initial investigations and completed the design for repairs to the damaged Peninsula boardwalk and bulkhead. On September 22, 2026, the completed plans were provided to on-call contractor Bitech Construction, and construction is anticipated to begin in early or mid-October. On September 25, 2026, the City gave the Mayor and City Council an update on the Hurricane Marie response and next steps, including the boardwalk and bulkhead repairs.