El Dorado Park Sports Field Improvements

El Dorado Park Sports Field Improvements photo 2

Additional project updates and information will be published on an on-going basis.

Click here for project updates.

Background

The El Dorado Sports Fields Improvements are part of a larger initiative to upgrade and revitalize El Dorado Regional Park in northeast Long Beach. Improvements to the youth softball and baseball fields and the surrounding areas were conducted in two phases. The planning and design were completed by the City of Long Beach Department of Public Works and Parks, Recreation and Marine Department, in partnership with the Sports Office and representatives from Los Altos Youth Baseball and Softball.

This project is part of the Elevate ’28 Infrastructure Investment Plan, a historic initiative dedicated to enhancing Long Beach parks, community facilities, mobility access, and streets. Learn more at lbelevate28.com.

For more information on all improvements at El Dorado Regional Park, click here.

Timeline

Permitting Spring 2024
Detailed Design and Construction Documentation Spring 2024
Begin Construction July 2024
Construction Completion Summer 2025

Project timeline is set barring weather delays and other unforeseen circumstances.

Objectives

  • Enhance the player and fan experience with updated field amenities
  • Improve accessibility and ADA compliance 
  • Modernize restroom facilities
  • Enhance visitor safety
  • Maintain the historical elements and importance of the complex
  • Upgrade the path of travel from the parking lot entrance 

Project Scope

Current Phase (Phase 2)

  • Renovated, individually accessible gender-neutral restroom stalls
  • Concrete pad around the swing gate and locking posts at the parking lot entrance
  • Replacement of three water fountains with hydration stations with bottle fillers
  • Refreshed amenities at Fields 5 and 6, including fresh paint, chain link fence and fabric, wood back boards, dugout benches, netting, sideline fencing, yellow topper pads, and backstop pads

Phase 1 (completed)

  • Updated backstops at Fields 1 through 4, with new infield fencing, netting, backboards, screening and dugout seating
  • Refreshed posts and resurfaced ballfield quad pavement between Fields 1 through 4 and the connecting pathway at Field 5
  • Laser graded infields at Fields 3 through 6
  • New entry point fencing to prevent unauthorized vehicle access to the quad area
  • Updated electrical equipment enclosure fencing at Field 6

Project Funding

Funding Source Amount
State Funding $2,800,000
Measure A $500,000

Phase 1 of this project was funded with $1.2 million from a $12.5 million State of California budget surplus allocation secured by Senator Lena Gonzalez, Assembly Speak Anthony Rendon and Assemblymember Patrick O’Donnell in Fiscal Year 2022.

Phase 2 was funded by an additional $1.6 million through California State Parks from the Fiscal Year 2023 State of California budget, appropriated by City Council for this project.

Phase 3 will be funded with $500,000 of FY27 with Measure A Bonds.

Project Contact

Jayson Lacno-Musngi, Capital Projects Coordinator
(562) 570-5578
Jayson.Lacno-Musngi@longbeach.gov

More Information

Latest Updates

April 2025

The construction by the City’s contractor, Blue Nose Construction is scheduled to be completed by Summer 2025, barring weather delays or other unforeseen circumstances. 

June 2024

The City’s Contractor, Blue Nose Construction is scheduled to begin construction in the area on July 15th, 2024.

The improvements will include: 

  • Renovation of existing standalone restroom with updated finishes, fixtures, openings. 

  • Updating 3 existing water fountains to be hydration stations and include bottle fillers 

  • ADA improvements at parking lot