Home Public Works Projects and Programs Fire Station 9

Fire Station 9

Background

The new Fire Station 9 location at 4101 Long Beach Blvd. is a two-story, state-of-the-art facility that will support the Fire Department in keeping the surrounding community safe during emergencies. The 12,779-square-foot building replaces a previously demolished office building that was on the site and will feature drought tolerant landscaping, water-efficient irrigation and fresh concrete paving, among other features. The mature trees on the west side of the property will remain in place.

The relocation of Fire Station 9 will also bring off-site improvements to the surrounding streets and alleys, detailed in the Project Features section below.

This project is part of the Elevate ’28 Infrastructure Investment Plan, a historic initiative dedicated to enhancing Long Beach parks, community facilities, mobility access, and streets. Learn more at lbelevate28.com.

Timeline

Bid and Award May 2024
Construction Start July 2024
Abatement and Demolition August 2024
Building Shell and Core December 2025
On-site Sitework Improvements August 2026
Off-site Improvements August 2026
Building Finishes September 2026
Construction Complete September 2026
Project timeline is set barring weather delays and other unforeseen circumstances. 

Objectives

  • Build a new, state-of-the-art fire station to replace the Fire Station 9 location that closed in 2019
  • Provide a safe, comfortable space for firefighters to rest, store equipment, and prepare to respond to emergencies from
  • Upgrade infrastructure onsite and surrounding area to improve public safety and site access

Proposed Features

  • New two-story, 12,779-square-foot fire station building
  • Enhanced site features, including upgraded landscaping, paving, lighting, trash enclosure, transformer, fencing and gates
  • Installation of new traffic signals at the intersection of Long Beach Boulevard and E. Randolph Place
  • Alley improvements on the north side of the facility, feature new pavement and two-and-a-half-foot widening
  • New concrete pavement along the section of E. Randolph Place on the southern side of the site
  • Upgraded sidewalks with new frontage and landscaping along Long Beach Boulevard and E. Randolph Place
  • Undergrounding of power lines along Long Beach Boulevard at the fire station

Project Funding

This project is funded by Measure A, Measure A bonds, and general capital.

More Information

Project Updates

August 2026

Construction of the new Fire Station 9 is entering its final phase, with significant progress made both inside and outside the facility. A major milestone was recently achieved with the connection of permanent electrical power, allowing the project team to begin commissioning and testing the building's mechanical, electrical, plumbing, fire protection, and life safety systems. The team is working toward obtaining a Temporary Certificate of Occupancy by early September, with final Certificate of Occupancy anticipated by the end of September 2026. 

The construction completion date has been updated to September to allow time for the delivery and installation of custom perimeter fence panels, which have experienced longer-than-anticipated procurement times. In the meantime, crews continue to complete interior finishes, landscaping, site improvements, and final details as the City prepares to open a modern fire station that will enhance emergency response and serve the Long Beach community for decades to come.

Contact Us About the Project

All Fields Required:

CAPTCHA: enter the characters shown in the image