Alamitos Bay Entrance Channel Dredge Project
Click here for project updates.
Background
The Alamitos Bay Entrance Channel Dredge Project will maintain safe navigation for boaters, and as part of this multi-benefit project, will stabilize the shoreline at Peninsula Beach. This effort is essential to maintaining vessel access into Alamitos Bay and supporting the City’s marinas, boating facilities, and waterfront destinations, including Marine Stadium, Spinnaker Bay, Davies Launch Ramp, Naples Island, and the Alamitos Bay Marina.
It has been more than 20 years since the entrance channel was last dredged. Over time, natural coastal processes have caused sand and sediment to build up along the shoreline and within the channel, creating shallow areas that make navigation more difficult and increase safety risks for boaters. The project will restore the federally authorized channel depths, which are approved by the regulatory agencies including the U.S. Army Corps of Engineers, the California Coastal Commission, and the Regional Water Quality Control Board.
In addition, dredged material will be sustainably reused to nourish the shoreline along Peninsula Beach, between 61st Place and the Jetty at 72nd Place. This environmentally preferred practice for dredging aligns with regional sediment management practices, and helps combat erosion, preserve recreational space and coastal access. This project represents an important investment in the city’s waterways and coastline, supporting both safe navigation and the long-term health of Peninsula Beach.
Due to the City's emergency response, parking at the 72nd Place lot will be restricted as signed in the field. City crews and contractors supporting the dredging activities will be staged at this lot.
Timeline
| Pre-Construction Activities | September - Mid-October 2026 |
| Construction Start | Staging October 14, 2026 Dredging October 20, 2026 |
| Construction End | February 2027 (Contractual) |
Project timeline is set barring weather delays and other unforeseen circumstances.
Objectives
- Provides safer vessel access into Alamitos Bay
- Align with sustainable sediment management practices and regulatory requirements for the Los Angeles region
- Expands usable beach areas, preserving recreational opportunities and coastal access
Project Features
Dredging- Sediments deposited in the entrance channel over the past 20 years will be removed to restore safe navigable depths and authorized dredge depths.
- Suitable sand from the dredging operation will be hydraulically pumped to Peninsula Beach, where it will be distributed along the shoreline to nourish the beach, consistent with sediment management guidelines by the regulatory agencies
FAQ
The City is pursuing a seven-point plan that combines immediate bulkhead repairs, beach nourishment, interim protective measures, and long-term adaptation planning along with necessary funding strategies. The second point of this plan is a previously planned maintenance dredging and beach nourishment project. This effort will restore safe, navigable depths in the Alamitos Bay entrance channel.
The work will hydraulically dredge 415,000 cubic yards of sandy material from the bay floor of the Alamitos Bay entrance channel (located between the two jetties) to restore navigable depths and beneficially reuse dredge spoils as beach nourishment along the Peninsula. Prior to Hurricane Marie, beach nourishment was expected to span from 61st Place to 72nd Place. Given the most recent beach profile changes from the various events, a new round of topographic and bathymetric surveys were completed prior to the dredging and nourishment activities.
The Long Beach Department of Public Works is overseeing various efforts and projects in preparation for and response to weather events. Manson Construction was determined to be the lowest and responsive bidder and was awarded a Contract by the City Council on August 11.
It has been more than 20 years since the channel was last dredged. Natural coastal processes have deposited sediment that creates shoals, making navigation more difficult, especially at lower tides. These shallow areas pose safety risks to boaters.
It is a multi-benefit project. It maintains safe navigation for boaters and stabilizes the shoreline at Peninsula Beach.
Manson Construction mobilized temporary construction fencing, certain equipment and office trailers throughout the week of October 12. Concurrently, crews also performed the necessary pre-construction topographic and bathymetric surveys. Dredging began on October 20, barring weather or unforeseen conditions. The contract duration allows work to be completed by early 2027. However, Manson is accelerating the job through the utilization of larger equipment and working extended hours.
A laydown and staging area supporting waterside and landside operations is established at the 72nd Place Beach Parking Lot.
Manson’s 211-ft cutter-suction dredge, the H.R. Morris completed a job in Oceanside, CA and arrived in Long Beach, CA on October 20. The Morris will be supported by the 115-ft derrick barge, DB Freya to address and remove various types of debris and impediments typically encountered during dredging operations. The Morris will be moored with a 5-anchor system and supported by smaller workboats (Pup and Cub) to help reposition the dredge along various segments within the entrance channel.
The H.R. Morris is a hydraulic cutter-suction dredge and removes sediment from the bay floor and hydraulically pumps this material through a series of piping stemming from the vessel, including a floating hose and shore piping which will run over the existing jetty onto the beach. The project will remove over 20 years of accumulated sediment and restore the channel depths to federally authorized elevations. Dredge production rates are dependent on unforeseen materials encountered during the dredging operations and possible impacts to the dredge pumps, but is expected to be approximately 20,000 cubic yards daily.
Crews are expected to pump, barring unforeseen conditions, approximately 20,000 cubic yards of material daily into constructed sand dikes on the beach. The sand dikes are expected to retain the material until enough volume is generated to begin grading to meet an average beach profile of 20:1 (a gradual slope towards the sea). Crews will then utilize two dozers to spread the pumped sand slurry, which is expected to widen the beach as the work progresses. The ultimate beach profile and width will depend on baseline, pre-construction conditions which will be captured the week of October 12 and anticipated weather impacts during the time of construction.
Prior to Hurricane Marie, the nourishment design expected to widen the beach by approximately 260 ft., creating a back beach elevation of +10 ft Mean Lower Low Water (MLLW), a generally accepted tidal datum for coastal projects, for approximately 150-175 ft. The limits of nourishment are expected to occur between 61st Place to 72nd Place pending new survey data after recent storm conditions and may need to be adjusted based on baseline conditions relative to available sand material and volume.
Yes. The dredged material was determined to be suitable and compatible for local, beneficial reuse. As required by State and Federal regulatory and resource agencies, dredging projects are reviewed by the Southern California Dredge Material and Management Team (SC-DMMT). The SC-DMMT reviewed all proposed dredging plans, sediment chemistry testing results, and sediment composition and confirmed dredged materials are suitable for reuse as beach nourishment along Peninsula Beach.
State and Federal agencies prioritize the beneficial reuse of suitable dredge materials to support local habitat and restore shorelines instead of offshore and landfill disposal. Placement of dredge spoils at Peninsula Beach is the environmentally preferred approach. It aligns with regional sediment management practices and helps combat erosion.
The total project cost is $11.4 million and is fully funded. Approximately $10.8M was budgeted through the Marina Fund, a self-supporting enterprise fund dedicated to the operation, maintenance, improvement, and financial management of the City’s municipal marina system. Approximately $600,000 is also budgeted through the Tidelands funds. The Tidelands and Marina Funds are separate from the General Fund.
They are separate projects and were necessitated from different circumstances. The maintenance dredging project was initiated in 2023 to restore navigable dredge depths within the Alamitos Bay entrance channel and is expected to utilize dredge spoils as beach nourishment material along the Peninsula.
The bulkhead/boardwalk repairs are emergency repairs, which were initiated after Hurricane Marie, and the scope is expected to expand to address damage encountered after Tropical Storm Rachel. The nourishment project may support conditions to better facilitate bulkhead repair construction.
The City, working with coastal engineering firm, Moffatt & Nichol, is designing a low-profile rock revetment to be placed along the most vulnerable areas of the Peninsula. The rock revetment is expected to dissipate wave energy and reduce direct impacts to the bulkhead in the face of future storms, southerly swells, and in a scenario of rapid coastal erosion. This is the fourth point of the City’s seven-point plan responding to Hurricane Marie and subsequent weather events.
Access a comprehensive update on City response and efforts related to recent weather events here.
Project Funding
This project is supported by Tidelands Capital and Tidelands Marina funds.
Contact
For project inquiries, please contact TidelandsCIP@longbeach.gov.
For media inquiries, please reach out to lbpwmedia@longbeach.gov.
Project Updates
Week of 11/9/26
The dredge vessel, H.R. Morris, returned from regularly scheduled maintenance and resumed dredging operations in the early afternoon of Monday, November 9.
The Alamitos Bay Entrance Channel Dredge project remains ahead of schedule, with work anticipated to be completed by the end of November, 2026.
Week of 11/2/26
Dredging operations are temporarily on hold while the dredge vessel (H.R. Morris) undergoes maintenance and repairs at the Port of Long Beach. Dredging operations paused in the early hours of October 29, and Manson Construction currently anticipates the vessel will return to the project site around November 11.
As of October 29, approximately 160,000 cubic yards of the total 415,000 cubic yards of planned dredging have been completed.
In the meantime, daytime beach operations are continuing to maintain the temporary sand berms and support ongoing shoreline work.
The project remains ahead of schedule, and the vessel's maintenance period is not anticipated to affect the overall project timeline, with completion still anticipated by the end of November.
Week of 10/26/26
The Alamitos Bay Entrance Channel Dredge project began on October 20 and has already added visible beachfront along the Peninsula, with more than 140,000 cubic yards of sand dredged to date.
Dredging and sand placement operations are continuing 24 hours a day, moving from the easternmost portion of the Peninsula toward the west to reach highly impacted areas. Sand is currently being graded along the beach to approximately 66th Place, with temporary sand berms constructed to help retain and direct the material.
The project is initially focusing on creating a narrower stretch of beach to advance west as quickly as possible and connect with the City’s Department of Parks, Recreation and Marine sand-moving operations. Once the crews connect, they will return to widen the beach. The project is anticipated to restore between 200-250 feet of beach width in the most critical areas, with narrower widths in less impacted sections of the Peninsula.
While the project is designed to improve beach conditions, beach width is influenced by tides, wave action and storm events, including the recent storms that have affected shoreline conditions, and those natural forces will continue to shape the beach over time.
For additional information about the vessels supporting dredging operations, project funding, anticipated timeline and other frequently asked questions, please refer to the FAQ above.
Week of 10/19/26
Manson Construction mobilized landside operations on Wednesday, October 14. On Tuesday October 20 at approximately 3 p.m., the H.R. Morris, a 211-foot cutter-suction dredge, arrived to Alamitos Bay.Supported by two work boats, the Morris was aligned into position and crews established the initial steel pipe run necessary to support hydraulic dredging operations and to transport dredged material from the bay floor to the beach. The pipe currently runs over the existing revetment structure and terminates at the stable beach at 72nd Place. At approximately 7 p.m. on October 20, Manson began hydraulic dredging and placement of material at 72nd Place. Work began at this location as a stable beach width is required to lay pipeline and construct sand dikes.
Manson will use initial pumped sediment to construct a sand dike, which will retain dredged material until enough sediments have accumulated to begin grading activities. Crews are expected to repeat this process of constructing sand dikes and pumping material until enough sediments have accumulated prior to beach grading.
For additional information about the vessels supporting dredging operations, project funding, anticipated timeline and other frequently asked questions, please refer to the FAQ above.
Construction on the Alamitos Bay Entrance Dredging project is anticipated to begin in October. As part of the project, suitable sand recovered through the dredging operation will be placed at Peninsula Beach and distributed along the shoreline to beneficially reuse material and nourish the eroded shoreline. During construction, parking at the 72nd Place main public lot will be reduced to accommodate contractor staging; however, access and circulation will be maintained. The overflow parking at 72nd Place lot will remain fully available. The project team will make efforts to minimize disruptions and maintain access throughout construction.
The City of Long Beach completed regulatory permitting and engineering designs for the subject project and received two contractor bids for the dredging and nourishment work. However, the bids received far exceed the City’s available and approved budget. The Public Works Department is evaluating opportunities to reduce costs based on feedback received from the contractor community during the bidding period. Public Works will work with the authorities having jurisdiction (AHJ) to request an extension of work hours for offshore dredging and onshore beach nourishment work to achieve efficiencies and cost savings, while remaining in compliance with the City’s ordinances. In addition, Public Works is in the process of submitting a climate grant pre-application to the State of California for this effort to help bridge the funding gap in the work. Upon receipt of waivers and/or exemptions, the City aims to re-advertise the project for bidding pursuant to the public contract code.